Huge dome lifted onto Hinkley Point C nuclear reactor | Huge dome lifted onto Hinkley Point C nuclear reactor |
(32 minutes later) | |
Hundreds of people helped with the delicate operation to get the 245-tonne steel dome into position | Hundreds of people helped with the delicate operation to get the 245-tonne steel dome into position |
A 245-tonne dome has been lifted onto a reactor building at the first nuclear plant to be built in Britain for 30 years. | A 245-tonne dome has been lifted onto a reactor building at the first nuclear plant to be built in Britain for 30 years. |
EDF Energy said twin nuclear reactors at Hinkley Point C in Somerset would provide zero-carbon electricity for more than six million homes in Britain when the site opened. | EDF Energy said twin nuclear reactors at Hinkley Point C in Somerset would provide zero-carbon electricity for more than six million homes in Britain when the site opened. |
The second dome was installed earlier using a "build and repeat" method, using off-site prefabrication and experience from installing the first dome on the first reactor. | The second dome was installed earlier using a "build and repeat" method, using off-site prefabrication and experience from installing the first dome on the first reactor. |
The site is projected to open in 2031, according to EDF, which is five years later than originally planned. | The site is projected to open in 2031, according to EDF, which is five years later than originally planned. |
Work on Hinkley Point C's second reactor building was stopped during the pandemic but EDF said teams were using time-saving methods to catch up. | Work on Hinkley Point C's second reactor building was stopped during the pandemic but EDF said teams were using time-saving methods to catch up. |
The power plant's second reactor is being built 20-30% more quickly than its first, EDF said | The power plant's second reactor is being built 20-30% more quickly than its first, EDF said |
The team said the second reactor was in a more complete state than the first reactor was when its roof was fitted 18 months ago. | |
And the company said construction on the second unit used 30% fewer people to achieve 40% more work compared to the first unit. | And the company said construction on the second unit used 30% fewer people to achieve 40% more work compared to the first unit. |
'Big Carl', the world's largest crane, lowered the dome onto Hinkley Point C's second reactor building | 'Big Carl', the world's largest crane, lowered the dome onto Hinkley Point C's second reactor building |
Stuart Crooks, CEO of Hinkley Point C, said: "Restarting the industry has been hard, but the second of our two identical units shows the big benefits of repeating an identical design. | Stuart Crooks, CEO of Hinkley Point C, said: "Restarting the industry has been hard, but the second of our two identical units shows the big benefits of repeating an identical design. |
"The build and repeat method is the best way to build new nuclear with time savings already at 20-30%." | "The build and repeat method is the best way to build new nuclear with time savings already at 20-30%." |
Energy minister Michael Shanks added: "Hinkley Point C will deliver the next generation of clean, homegrown nuclear power, creating high quality jobs and growth in Somerset and across its supply chains." | Energy minister Michael Shanks added: "Hinkley Point C will deliver the next generation of clean, homegrown nuclear power, creating high quality jobs and growth in Somerset and across its supply chains." |