This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.
You can find the current article at its original source at http://www.bbc.co.uk/news/business-42056246
The article has changed 5 times. There is an RSS feed of changes available.
Version 3 | Version 4 |
---|---|
Nebraska approves Keystone XL pipeline | Nebraska approves Keystone XL pipeline |
(about 9 hours later) | |
Nebraska regulators have approved the Keystone XL pipeline, clearing the way for the controversial and long-delayed project to progress. | Nebraska regulators have approved the Keystone XL pipeline, clearing the way for the controversial and long-delayed project to progress. |
Commissioners voted 3-2 in favour of the project, which will link Canada's oil sands to US refineries. | |
The decision comes days after a leak in the existing Keystone network spilled 210,000 gallons in South Dakota. | The decision comes days after a leak in the existing Keystone network spilled 210,000 gallons in South Dakota. |
The pipeline is backed by US President Donald Trump but opposed by environmentalists and some landowners. | The pipeline is backed by US President Donald Trump but opposed by environmentalists and some landowners. |
Former President Barack Obama had rejected the project in 2015 on environmental grounds, but President Trump reversed the decision earlier this year. | Former President Barack Obama had rejected the project in 2015 on environmental grounds, but President Trump reversed the decision earlier this year. |
That left the regulatory fate of the 1,179-mile (1,897-km) pipeline in the hands of Nebraska's Public Service Commission. | That left the regulatory fate of the 1,179-mile (1,897-km) pipeline in the hands of Nebraska's Public Service Commission. |
On Monday, the commissioners voted to approve the "mainline alternative route", slightly different from the route preferred by TransCanada, the firm spearheading the project. | |
Unlike the preferred route, the alternative route heads farther east for part of its travel through the state, more closely matching the path of the existing pipeline. | Unlike the preferred route, the alternative route heads farther east for part of its travel through the state, more closely matching the path of the existing pipeline. |
TransCanada said in a statement that it would "conduct a careful review" of the ruling while assessing how the decision would impact the cost and schedule of the project. | |
Keystone XL pipeline: Why is it so disputed? | Keystone XL pipeline: Why is it so disputed? |
Drone footage captures extent of US oil leak | Drone footage captures extent of US oil leak |
Canada's federal Natural Resources Minister Jim Carr said the approval "bolsters North American energy security and economic competitiveness". | |
Alberta Premier Rachel Notley said the pipeline's approval is a positive step towards diversifying the market for Canada's oil. | |
The decision is subject to appeal. TransCanada is also reviewing demand from shipping firms. | The decision is subject to appeal. TransCanada is also reviewing demand from shipping firms. |