Norwich roads closed as bumps too low to slow traffic are rebuilt Norwich roads closed as bumps too low to slow traffic are rebuilt
(about 4 hours later)
Speed bumps which were constructed as part of a £320,000 scheme will be rebuilt due to them being too low.Speed bumps which were constructed as part of a £320,000 scheme will be rebuilt due to them being too low.
Some of the traffic-calming humps, which were built in Norwich, were only 35mm tall, which is deemed too flat to slow down traffic. Some of the traffic-calming humps, which were built in Norwich, were only 3.5cm (1.4in) tall, which is deemed too flat to slow down traffic.
Contractor Tarmac will rebuild the bumps, as first reported by the EDP, causing fresh road closures.Contractor Tarmac will rebuild the bumps, as first reported by the EDP, causing fresh road closures.
Transport for Norwich said it was "disappointed" the scheme had not been carried out in line with the designs.Transport for Norwich said it was "disappointed" the scheme had not been carried out in line with the designs.
Six humps were installed on Waterloo Road and five on Angel Road during work last summer as part of a project which also saw improvements to road surfaces and cycle paths.Six humps were installed on Waterloo Road and five on Angel Road during work last summer as part of a project which also saw improvements to road surfaces and cycle paths.
The bumps should have been 75mm tall to successfully slow traffic. The bumps should have been 7.5cm (3in) tall to successfully slow traffic.
A Transport for Norwich spokeswoman said: "We are obviously disappointed that the speed humps on Angel Road weren't constructed in line with the original design. Our contractor, Tarmac, has responded to the request for this to be corrected and will also be covering the cost for the work."A Transport for Norwich spokeswoman said: "We are obviously disappointed that the speed humps on Angel Road weren't constructed in line with the original design. Our contractor, Tarmac, has responded to the request for this to be corrected and will also be covering the cost for the work."
Tarmac will carry out the remedial work, set to take 10 days from Tuesday, at no extra cost and has apologised for the inconvenience.Tarmac will carry out the remedial work, set to take 10 days from Tuesday, at no extra cost and has apologised for the inconvenience.