Royal Liverpool Hospital: Structural flaws at £335m hospital | Royal Liverpool Hospital: Structural flaws at £335m hospital |
(about 7 hours later) | |
Three floors at a stalled new hospital must be rebuilt because of "complex" structural flaws left by construction giant Carillion, a review has found. | Three floors at a stalled new hospital must be rebuilt because of "complex" structural flaws left by construction giant Carillion, a review has found. |
Building work at the already delayed new Royal Liverpool Hospital was halted in February last year after Carillion's collapse. | Building work at the already delayed new Royal Liverpool Hospital was halted in February last year after Carillion's collapse. |
The review by structural engineers from Arup found three of 11 floors require strengthening. | The review by structural engineers from Arup found three of 11 floors require strengthening. |
The hospital was originally due to open in March 2017. | The hospital was originally due to open in March 2017. |
Dr Peter Williams, chief executive of the Royal Liverpool and Broadgreen University Hospitals NHS Trust, said a new completion date had not been set to avoid "raising expectations". | Dr Peter Williams, chief executive of the Royal Liverpool and Broadgreen University Hospitals NHS Trust, said a new completion date had not been set to avoid "raising expectations". |
The work will involve "stripping back" areas that were near to completion, the trust said. | The work will involve "stripping back" areas that were near to completion, the trust said. |
The Department of Health has been contacted for a response on behalf of Carillion. | The Department of Health has been contacted for a response on behalf of Carillion. |
Repeatedly delayed | Repeatedly delayed |
The project, a 646-bed hospital originally expected to cost £335m, has been repeatedly delayed after asbestos was found on site and remedial building work was also needed. | The project, a 646-bed hospital originally expected to cost £335m, has been repeatedly delayed after asbestos was found on site and remedial building work was also needed. |
Structural work, which will begin later this month, includes strengthening existing beams, reducing loads and putting in additional support for torsions, Jim Bell, director of structural engineers for Arup, said. | Structural work, which will begin later this month, includes strengthening existing beams, reducing loads and putting in additional support for torsions, Jim Bell, director of structural engineers for Arup, said. |
Mr Bell said it was "highly complex" and required more than 220 cubic metres of new concrete and 165 tonnes of new fabricated steelwork. | Mr Bell said it was "highly complex" and required more than 220 cubic metres of new concrete and 165 tonnes of new fabricated steelwork. |
New contractors Laing O'Rourke, who also built Liverpool One and Alder Hey Children's Hospital, said they were working to finish the building "to the high standards required". | New contractors Laing O'Rourke, who also built Liverpool One and Alder Hey Children's Hospital, said they were working to finish the building "to the high standards required". |
Control measures are already in place so that there are no immediate risks to workers in the building, project director Andy Thomson added. | Control measures are already in place so that there are no immediate risks to workers in the building, project director Andy Thomson added. |
Some of the cladding of the new hospital will be removed for access. | Some of the cladding of the new hospital will be removed for access. |
Dr Williams said: "Once the programme [to complete the new Royal] is finalised and the costs are all accounted for we'll confirm timescales and costs. | Dr Williams said: "Once the programme [to complete the new Royal] is finalised and the costs are all accounted for we'll confirm timescales and costs. |
"We owe it to everyone to not raise expectations with speculation, until everything is signed, sealed and delivered. | "We owe it to everyone to not raise expectations with speculation, until everything is signed, sealed and delivered. |
"Our priority is to deliver the state of the art facilities that our patients need and the world class hospital we've all been waiting for." | "Our priority is to deliver the state of the art facilities that our patients need and the world class hospital we've all been waiting for." |
Liverpool Mayor Joe Anderson said it was a "shambles", adding: "In 2010 the government reduced and took away the right of local authorities to inspect buildings in the private sector. | |
"That is why I'm calling for an inquiry into why this was allowed to happen." | |
Dame Louise Ellman, MP for Liverpool Riverside, said: "Carillion's calamitous collapse left Liverpool in the lurch." | Dame Louise Ellman, MP for Liverpool Riverside, said: "Carillion's calamitous collapse left Liverpool in the lurch." |
"It is deeply disappointing that the discovery of significant construction defects will result in further delay," she added. | "It is deeply disappointing that the discovery of significant construction defects will result in further delay," she added. |
"The new Royal should have opened two years ago. | "The new Royal should have opened two years ago. |
"It is vital for the necessary work to be completed as a matter of urgency, so that the people of Liverpool can have this much-needed new facility." | "It is vital for the necessary work to be completed as a matter of urgency, so that the people of Liverpool can have this much-needed new facility." |