Ely Junction railway upgrade cost rises more than 20 times | Ely Junction railway upgrade cost rises more than 20 times |
(about 1 hour later) | |
The estimated cost of a major railway upgrade has risen to £500m, 20 times the original estimate. | The estimated cost of a major railway upgrade has risen to £500m, 20 times the original estimate. |
The upgrade to the Ely North junction, a connection point for East Anglia with London and the Midlands, was supposed to start in 2017 but has yet to begin. | The upgrade to the Ely North junction, a connection point for East Anglia with London and the Midlands, was supposed to start in 2017 but has yet to begin. |
The work was originally due to cost £25m, but the BBC understands a Network Rail report found an increase in cost. | The work was originally due to cost £25m, but the BBC understands a Network Rail report found an increase in cost. |
Network Rail said the original scheme "wouldn't release the additional services" needed by rail users. | |
A spokeswoman added: "A far wider range of interventions is required including layout changes at Ely station, improvements to bridges, power upgrades and improvements to level crossings, in order to fully meet demands." | |
The BBC has contacted the Department for Transport (DfT) for comment. | |
If the upgrade was to go ahead it could be possible to run more trains between Norwich and Cambridge; King's Lynn and London; Ipswich and Peterborough, along with extra freight services between the port of Felixstowe and the Midlands. | If the upgrade was to go ahead it could be possible to run more trains between Norwich and Cambridge; King's Lynn and London; Ipswich and Peterborough, along with extra freight services between the port of Felixstowe and the Midlands. |
'Critical junction' | 'Critical junction' |
The report is understood to reveal that as well as extra track, a new bridge will have to be built, while Ely station and the Queen Adelaide junction will need remodelling. | The report is understood to reveal that as well as extra track, a new bridge will have to be built, while Ely station and the Queen Adelaide junction will need remodelling. |
More than 100 level crossings in the area will also need upgrading, the report said. | More than 100 level crossings in the area will also need upgrading, the report said. |
In 2017 Network Rail said the work would start between 2019 and 2024. | In 2017 Network Rail said the work would start between 2019 and 2024. |
Despite the rise in cost, the chairman of Transport East Kevin Bentley said: "We've got to make sure that we are still pushing for this. This is a critical junction on the east-west route. | Despite the rise in cost, the chairman of Transport East Kevin Bentley said: "We've got to make sure that we are still pushing for this. This is a critical junction on the east-west route. |
"We have poor east-west links, we have been forgotten about, we have been under-invested in in this region. That has now got to stop." | "We have poor east-west links, we have been forgotten about, we have been under-invested in in this region. That has now got to stop." |
Network Rail said it would put its further plans to the DfT "in the spring". |