Tram bill could escalate to £750m | Tram bill could escalate to £750m |
(about 16 hours later) | |
The final cost of Edinburgh's tram project could reach £750m - £250m more than originally planned, according to an MSP. | |
SNP MSP Shirley Anne Somerville also said sources close to the project said trams may not start running until 2013, two years later than expected. | SNP MSP Shirley Anne Somerville also said sources close to the project said trams may not start running until 2013, two years later than expected. |
She called on project manager Tie to release latest cost figures. | She called on project manager Tie to release latest cost figures. |
Edinburgh City Council leader, Jenny Dawe said Ms Somerville was "purely scaremongering". | Edinburgh City Council leader, Jenny Dawe said Ms Somerville was "purely scaremongering". |
The project's cost was originally estimated at £498m. | The project's cost was originally estimated at £498m. |
The nationalist MSP for the Lothians, Shirley Anne Somerville, said: "I am very concerned that a number of sources I have been speaking to close to the project are estimating large overruns with the largest being £750m as the worst case scenario. | The nationalist MSP for the Lothians, Shirley Anne Somerville, said: "I am very concerned that a number of sources I have been speaking to close to the project are estimating large overruns with the largest being £750m as the worst case scenario. |
"But even the best case scenario we are still looking at £650m. | "But even the best case scenario we are still looking at £650m. |
"On the delivery date, we are looking at some people suggesting 2013, which is a two year delay on the trams being up and running. | "On the delivery date, we are looking at some people suggesting 2013, which is a two year delay on the trams being up and running. |
"I think the people have a right to know how much this project will cost and they will lose faith in the new management of Tie unless they get that information." | "I think the people have a right to know how much this project will cost and they will lose faith in the new management of Tie unless they get that information." |
Shirley Anne Somerville called on Tie to release latest cost figures | |
Jenny Dawe, Edinburgh City Council leader, said: "The funding situation and projected delivery date for trams running on the street has not changed since being reported to the council last month. | Jenny Dawe, Edinburgh City Council leader, said: "The funding situation and projected delivery date for trams running on the street has not changed since being reported to the council last month. |
"The dispute resolution process is currently underway and both the council and Tie are committed to ensuring that we come in as close to budget as possible. | "The dispute resolution process is currently underway and both the council and Tie are committed to ensuring that we come in as close to budget as possible. |
"Speculation from Ms Somerville is purely scaremongering - a fact backed up by her inability to substantiate her sources." | "Speculation from Ms Somerville is purely scaremongering - a fact backed up by her inability to substantiate her sources." |
Mandy Haeburn-Little, Tie spokeswoman, said: "Not only is this information incorrect but it is deeply damaging to the positive progress of the Edinburgh tram project. | Mandy Haeburn-Little, Tie spokeswoman, said: "Not only is this information incorrect but it is deeply damaging to the positive progress of the Edinburgh tram project. |
"Categorically there is nothing to suggest that the programme will extend beyond 2012 as had been stated publicly. | "Categorically there is nothing to suggest that the programme will extend beyond 2012 as had been stated publicly. |
"The programme is making good progress and is on track to be clear of Princes Street at the end of November as planned." | "The programme is making good progress and is on track to be clear of Princes Street at the end of November as planned." |