BBC 'overspends' on building work | BBC 'overspends' on building work | ||||
(about 2 hours later) | |||||
The BBC has been criticised for facing "serious difficulties" over its programme of major new building works. | The BBC has been criticised for facing "serious difficulties" over its programme of major new building works. | ||||
The extension of Broadcasting House has cost £100m more than planned and was due for completion in 2008, a National Audit Office report found. | The extension of Broadcasting House has cost £100m more than planned and was due for completion in 2008, a National Audit Office report found. | ||||
It added the project has suffered from "weak governance", while the BBC's Salford centre is set to be completed around £76m under budget. | It added the project has suffered from "weak governance", while the BBC's Salford centre is set to be completed around £76m under budget. | ||||
BBC Trustee Jeremy Peat admitted that licence fee payers were "let down". | BBC Trustee Jeremy Peat admitted that licence fee payers were "let down". | ||||
'Room for improvement' | 'Room for improvement' | ||||
The BBC is expected to carry out an imminent check on all its projects in the wake of the report. | The BBC is expected to carry out an imminent check on all its projects in the wake of the report. | ||||
It was commissioned by the BBC Trust, which is in place to ensure that value for money is delivered, and concluded the three building projects have failed to do so. | It was commissioned by the BBC Trust, which is in place to ensure that value for money is delivered, and concluded the three building projects have failed to do so. | ||||
Mr Peat admitted that "serious mistakes" had been made in the early part of the Broadcasting House project. | Mr Peat admitted that "serious mistakes" had been made in the early part of the Broadcasting House project. | ||||
"But there is still considerable room for improvement, and consequently we will follow up the National Audit Office's recommendations vigorously and as a matter of urgency," he added. | "But there is still considerable room for improvement, and consequently we will follow up the National Audit Office's recommendations vigorously and as a matter of urgency," he added. | ||||
The corporation is spending £2bn over a long term period on its new facilities. | The corporation is spending £2bn over a long term period on its new facilities. | ||||
The new broadcasting centre at Pacific Quay in Glasgow went over budget by £62m and faced a year's delay. | The new broadcasting centre at Pacific Quay in Glasgow went over budget by £62m and faced a year's delay. | ||||
The report recommended that for future projects "proposals submitted by management are reliable and subject to effective challenge by the BBC Trust". | The report recommended that for future projects "proposals submitted by management are reliable and subject to effective challenge by the BBC Trust". | ||||
It also revealed that the Broadcasting House project based around the existing building in central London faced problems from the outset after a dispute with the developer cost £45m to resolve. | It also revealed that the Broadcasting House project based around the existing building in central London faced problems from the outset after a dispute with the developer cost £45m to resolve. | ||||
The Pacific Quay project, which cost £188m, ran into delays and was part-funded by unused contingency money. | The Pacific Quay project, which cost £188m, ran into delays and was part-funded by unused contingency money. | ||||
It had been originally budgeted at £126m. | It had been originally budgeted at £126m. | ||||
But the report added that the BBC's management of the three major projects has subsequently improved. | But the report added that the BBC's management of the three major projects has subsequently improved. | ||||
BBC Director general Mark Thompson is expected to report his findings on the ongoing projects to the trust in the next month. | BBC Director general Mark Thompson is expected to report his findings on the ongoing projects to the trust in the next month. | ||||
Original budget | Final cost/Current forecast | Operational (target) | Pacific Quay, Glasgow £125.6m(May 2002) £188.1m(final cost)Jul 2007(June 06)Salford Quays, Manchester £953m(Dec 2006)£877m(forecast)Dec 2011(Dec 2011)Broadcasting House, London £991m(July 2003)£1,046m(forecast)Apr 2011(Dec 2008) | ||
SOURCE: NAO |