Sellafield Thorp plant to close | Sellafield Thorp plant to close |
(about 1 hour later) | |
Sellafield's Thermal Oxide Reprocessing Plant (Thorp) in Cumbria is to close in 2018, it has been confirmed. | |
The Nuclear Decommissioning Authority (NDA) said it had completed its strategic review of the options for the management of oxide fuels. | |
It said processing contracts would be completed by 2018, at which time Thorp would cease reprocessing activities prior to decommissioning. | It said processing contracts would be completed by 2018, at which time Thorp would cease reprocessing activities prior to decommissioning. |
Many of the 800 workers should be found work elsewhere at Sellafield, it added. | Many of the 800 workers should be found work elsewhere at Sellafield, it added. |
An NDA spokesman said it had published three options for the Thorp site in March last year which had been under consultation. | |
The options were to close Thorp without completing contracts, to close it after completing the contracts or to extend the life of the plant by looking for new contracts. | |
'No cliff edge' | |
The NDA board agreed with the preferred option of closing after completing the contracts. | |
The spokesman said the decision was due to falling demand for reprocessing and the relatively low cost of uranium. | |
If Thorp was to continue running beyond 2018 it would require a multi-billion pound upgrade, he added. | |
The spokesman said there would be "no cliff edge" of job losses in 2018 as once the plant stops operating there would be a two-year period of post operations. | |
The NDA said the review confirmed its position that completing the reprocessing contracts at Thorp remained a viable and cost-effective strategy. | The NDA said the review confirmed its position that completing the reprocessing contracts at Thorp remained a viable and cost-effective strategy. |
Oxide fuels include the remaining overseas-derived spent fuels that are being stored at Sellafield before reprocessing at Thorp and also the spent fuels from the UK's fleet of Advanced Gas-Cooled Reactor power stations, which are owned and operated by EDF Energy. | Oxide fuels include the remaining overseas-derived spent fuels that are being stored at Sellafield before reprocessing at Thorp and also the spent fuels from the UK's fleet of Advanced Gas-Cooled Reactor power stations, which are owned and operated by EDF Energy. |
The Thorp plant started operating in 1994. |