Health body 'omitted' key facts Health body to reveal key papers
(about 7 hours later)
NHS Lothian has been ordered to disclose full details of the £184m contract to build and run the new Royal Infirmary of Edinburgh.NHS Lothian has been ordered to disclose full details of the £184m contract to build and run the new Royal Infirmary of Edinburgh.
The Scottish Information Commissioner rejected NHS Lothian's claim the details were confidential.The Scottish Information Commissioner rejected NHS Lothian's claim the details were confidential.
Commissioner Kevin Dunion said the health board had "omitted" 5,000 pages of information to a Freedom of Information request.Commissioner Kevin Dunion said the health board had "omitted" 5,000 pages of information to a Freedom of Information request.
The health board said it would seek to comply with the order.
The hospital was financed through the Private Finance Initiative.The hospital was financed through the Private Finance Initiative.
Mr Dunion also said the board had incorrectly claimed the cost of providing the information would be excessive.Mr Dunion also said the board had incorrectly claimed the cost of providing the information would be excessive.
NHS Lothian provided me with virtually no arguments to justify withholding the contract Kevin DunionScottish Information CommissionerNHS Lothian provided me with virtually no arguments to justify withholding the contract Kevin DunionScottish Information Commissioner
The hospital was built by the Consort Healthcare Consortium - made up of Balfour Beatty Construction, Morrison Development and The Royal Bank of Scotland.The hospital was built by the Consort Healthcare Consortium - made up of Balfour Beatty Construction, Morrison Development and The Royal Bank of Scotland.
It officially opened in January 2003 and is rented back to NHS Lothian, who are charged for the running costs. It officially opened in January 2003 and is rented back to NHS Lothian, which is charged for the running costs.
NHS Lothian published some details of the £184m contract, but refused others on the grounds they were commercially confidential. NHS Lothian published some details of the £184m contract, but refused others on the grounds that they were commercially confidential.
One campaigner, May Docherty, appealed against that to the commissioner.One campaigner, May Docherty, appealed against that to the commissioner.
Mr Dunion said: "It is the responsibility of NHS Lothian to provide detailed justification for withholding the information requested.Mr Dunion said: "It is the responsibility of NHS Lothian to provide detailed justification for withholding the information requested.
"In this case it sought to claim that a blanket exemption of confidentiality covered every one of the thousands of pages of this detailed contract."In this case it sought to claim that a blanket exemption of confidentiality covered every one of the thousands of pages of this detailed contract.
"However, other than broadly indicating why Consort Healthcare did not wish the information disclosed, NHS Lothian provided me with virtually no arguments to justify withholding the contract."However, other than broadly indicating why Consort Healthcare did not wish the information disclosed, NHS Lothian provided me with virtually no arguments to justify withholding the contract.
"As a consequence I have ordered that the contract must be disclosed.""As a consequence I have ordered that the contract must be disclosed."