French railway operator SNCF orders hundreds of new trains that are too big French railway operator SNCF orders hundreds of new trains that are too big
(about 1 hour later)
The train due on platform one will not be arriving for the foreseeable future – because it is too big.The train due on platform one will not be arriving for the foreseeable future – because it is too big.
France's national railway operator SNCF has ordered 2,000 new trains that are too large for many of the stations they are due to serve.France's national railway operator SNCF has ordered 2,000 new trains that are too large for many of the stations they are due to serve.
The train operator has admitted failing to verify measurements it was given by the rail operator before ordering its new rolling stock.The train operator has admitted failing to verify measurements it was given by the rail operator before ordering its new rolling stock.
The costly mistake has sparked an urgent €50m operation to enlarge 1,300 platforms on the regional network. SNCF has admitted that one in six regional train stations is affected. In the worst cases it has discovered two trains can no longer pass each other on adjacent lines. The costly mistake has sparked an urgent €50m operation to modify 1,300 platforms on the regional network. SNCF has admitted that one in six regional train stations is affected. In the worst cases it has discovered two trains can no longer pass each other on adjacent lines.
The new regional trains, known as TERs (trains express regionaux), are intended to upgrade the network and were based on measurements provided by national rail operator RFF.However, RFF sent SNCF the dimensions of stations built less than 30 years ago. It was then discovered – after it was too late – that the trains, due to go into service from now until 2016, were too big by several centimetres for stations built more than 50 years ago.The new regional trains, known as TERs (trains express regionaux), are intended to upgrade the network and were based on measurements provided by national rail operator RFF.However, RFF sent SNCF the dimensions of stations built less than 30 years ago. It was then discovered – after it was too late – that the trains, due to go into service from now until 2016, were too big by several centimetres for stations built more than 50 years ago.
SNCF insisted only 341 trains – 182 from Alstom and 159 from a second company, Bombardier – were affected.SNCF insisted only 341 trains – 182 from Alstom and 159 from a second company, Bombardier – were affected.
However, satirical news magazine Le Canard Enchainé insisted 1,000 of the trains had been ordered from Alstom and 860 from Bombardier, making a total of 1,860 trains that were too wide for many of the stations they are to service.However, satirical news magazine Le Canard Enchainé insisted 1,000 of the trains had been ordered from Alstom and 860 from Bombardier, making a total of 1,860 trains that were too wide for many of the stations they are to service.
The French minister of transport described the situation as "absurd" and a "comic drama". He blamed the previous centre-right administration's decision to separate the rail network from the train network.The French minister of transport described the situation as "absurd" and a "comic drama". He blamed the previous centre-right administration's decision to separate the rail network from the train network.
The rail farce was revealed in Le Canard Enchaîné, which said: "The clever engineers at SNCF forgot to verify the facts on the ground."The rail farce was revealed in Le Canard Enchaîné, which said: "The clever engineers at SNCF forgot to verify the facts on the ground."
Christophe Piednoël, spokesperson for RFF, told France Info radio: "It's as if you have bought a Ferrari that you want to park in your garage, and you realise that your garage isn't exactly the right size to fit a Ferrari because you didn't have a Ferrari before. We discovered the problem a little late … we are making our mea culpa."Christophe Piednoël, spokesperson for RFF, told France Info radio: "It's as if you have bought a Ferrari that you want to park in your garage, and you realise that your garage isn't exactly the right size to fit a Ferrari because you didn't have a Ferrari before. We discovered the problem a little late … we are making our mea culpa."
SNCF and RFF said in a joint statement on Wednesday: "Putting this network of new generation and larger trains in order to satisfy public demand will require the modernisation of 1,300 platforms out of the 8,700 in the French rail network."SNCF and RFF said in a joint statement on Wednesday: "Putting this network of new generation and larger trains in order to satisfy public demand will require the modernisation of 1,300 platforms out of the 8,700 in the French rail network."
The economic newspaper Les Echos said: "It could have been an arithmetic exercise from the old days."The economic newspaper Les Echos said: "It could have been an arithmetic exercise from the old days."