This article is from the source 'bbc' and was first published or seen on . It will not be checked again for changes.

You can find the current article at its original source at http://news.bbc.co.uk/go/rss/-/1/hi/england/7195418.stm

The article has changed 5 times. There is an RSS feed of changes available.

Version 0 Version 1
Report over New Year rail delays Report over New Year rail delays
(about 5 hours later)
A report examining delays in engineering work which wrecked travel plans for thousands of people over New Year is to be published later.A report examining delays in engineering work which wrecked travel plans for thousands of people over New Year is to be published later.
Work on the West Coast line at Rugby and Nuneaton was delayed by four days and London's Liverpool Street station was shut for a day longer than planned. Work on the West Coast line at Rugby and Nuneaton was delayed by four days and London's Liverpool Street station was also shut for longer than planned.
Network Rail, which had overall control of the work, will publish the report.Network Rail, which had overall control of the work, will publish the report.
The investigation has run in parallel to one started by the Office of Rail Regulation (ORR).The investigation has run in parallel to one started by the Office of Rail Regulation (ORR).
The ORR's findings are expected to be published at the end of February.The ORR's findings are expected to be published at the end of February.
Passenger groupsPassenger groups
The work on the West Coast at Rugby and Nuneaton in Warwickshire closed a 40-mile section of the line and passengers were forced to take buses between Birmingham and Northampton.The work on the West Coast at Rugby and Nuneaton in Warwickshire closed a 40-mile section of the line and passengers were forced to take buses between Birmingham and Northampton.
Engineers should have finished by the end of 30 December, but Network Rail, which used contactors to carry out the repairs, said it needed another day to complete the £415m job.Engineers should have finished by the end of 30 December, but Network Rail, which used contactors to carry out the repairs, said it needed another day to complete the £415m job.
Work was not finished for a further three days, with full services not returning until 4 January.Work was not finished for a further three days, with full services not returning until 4 January.
There were also problems on services run by the One train company, with Liverpool Street station having to remain closed for 24 hours more than was originally planned. There were also problems on services run by the One train company, with Liverpool Street station having to remain fully closed for about half a day more than was originally planned.
'Learn lessons''Learn lessons'
Opposition MPs, business leaders and passenger groups have condemned Network Rail's handling of the engineering work.Opposition MPs, business leaders and passenger groups have condemned Network Rail's handling of the engineering work.
The company's chief executive, Iain Coucher, said earlier in the week: "We at Network Rail have taken responsibility and we reiterate our apology.The company's chief executive, Iain Coucher, said earlier in the week: "We at Network Rail have taken responsibility and we reiterate our apology.
"Nonetheless, I wanted personally to hear explanations from the relevant contractors."Nonetheless, I wanted personally to hear explanations from the relevant contractors.
"What happened was totally unacceptable and we have to learn lessons, so it does not happen again.""What happened was totally unacceptable and we have to learn lessons, so it does not happen again."
ORR fined Network Rail £2.4m for a signalling work overrun at Portsmouth in 2006.ORR fined Network Rail £2.4m for a signalling work overrun at Portsmouth in 2006.