This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.

You can find the current article at its original source at http://www.bbc.co.uk/news/uk-scotland-edinburgh-east-fife-35165201

The article has changed 9 times. There is an RSS feed of changes available.

Version 1 Version 2
Traffic returns to Forth Road Bridge Traffic returns to Forth Road Bridge
(about 1 hour later)
Traffic has returned to the Forth Road Bridge after the completion of temporary repairs.Traffic has returned to the Forth Road Bridge after the completion of temporary repairs.
The first cars were allowed back onto the crossing at 05:20 after engineers welded a splint onto damaged steelwork.The first cars were allowed back onto the crossing at 05:20 after engineers welded a splint onto damaged steelwork.
Heavy goods vehicles will remain banned until further work is carried out, with this scheduled for completion by "mid-February".Heavy goods vehicles will remain banned until further work is carried out, with this scheduled for completion by "mid-February".
The bridge was closed to all traffic on 4 December after a crack was discovered in a truss under the carriageway.The bridge was closed to all traffic on 4 December after a crack was discovered in a truss under the carriageway.
In normal operation, the bridge handles 70,000 vehicles each day and closure has caused significant disruption.In normal operation, the bridge handles 70,000 vehicles each day and closure has caused significant disruption.
The partial re-opening is ahead of schedule, with officials having previously estimated that the temporary repairs would not be completed until after the Christmas holidays.The partial re-opening is ahead of schedule, with officials having previously estimated that the temporary repairs would not be completed until after the Christmas holidays.
But the ban on HGV's is now longer than expected. Road Haulage Association chief executive Richard Burnett said it would have a "massive impact". But the ban on HGVs is longer than expected. Road Haulage Association chief executive Richard Burnett said it would have a "massive impact".
"The major distribution centres on the northern, Fife-side of the river are totally reliant on an efficient, swift transport system and we have had many reports from members who are already struggling to keep to their pre-Christmas delivery schedules," he said."The major distribution centres on the northern, Fife-side of the river are totally reliant on an efficient, swift transport system and we have had many reports from members who are already struggling to keep to their pre-Christmas delivery schedules," he said.
"The news that they will continue to face delays and a massive increase in cost for another eight weeks will, for many, prove to be unsustainable.""The news that they will continue to face delays and a massive increase in cost for another eight weeks will, for many, prove to be unsustainable."
Police officer stationed at both ends of the bridge on Wednesday were re-directing any vehicle over 7.5 tonnes. Chris MacRae from the Freight Transport Association said: "A lot of our members are going to be very upset to put it mildly, that they were planning for a fourth of January return and now it's an unspecified date in the midle of February.
"That cannot be allowed to slip again. It has to reopen to HGVs in the middle of February and we have to have a date for that as soon as possible."
Police officers were stationed at both ends of the bridge on Wednesday to redirect any vehicle over 7.5 tonnes.
A police spokesman said the continued ban on HGVs was being well adhered to.
HGVs account for 32% of the weight the bridge normally carries despite making up approx 9% of overall traffic.HGVs account for 32% of the weight the bridge normally carries despite making up approx 9% of overall traffic.
Rigorous testing
Transport Minister Derek Mackay said: "I am pleased that we are now able to reopen the bridge to 90% of traffic, well ahead of schedule.Transport Minister Derek Mackay said: "I am pleased that we are now able to reopen the bridge to 90% of traffic, well ahead of schedule.
"Following rigorous testing and inspection of the temporary repair, experts have recommended the bridge is now ready to open to all traffic except HGVs."Following rigorous testing and inspection of the temporary repair, experts have recommended the bridge is now ready to open to all traffic except HGVs.
"With the temporary solution now in place, the remaining work to install the long-term repair can safely proceed without the need for a full closure."With the temporary solution now in place, the remaining work to install the long-term repair can safely proceed without the need for a full closure.
"The repairs will be carried out with overnight lane restrictions on the bridge.""The repairs will be carried out with overnight lane restrictions on the bridge."