This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.

You can find the current article at its original source at http://www.bbc.co.uk/news/uk-scotland-edinburgh-east-fife-35165201

The article has changed 9 times. There is an RSS feed of changes available.

Version 5 Version 6
Traffic returns to Forth Road Bridge Traffic returns to Forth Road Bridge
(about 1 hour later)
Traffic has returned to the Forth Road Bridge after the completion of temporary repairs.Traffic has returned to the Forth Road Bridge after the completion of temporary repairs.
The first cars were allowed back onto the crossing at 05:20 after engineers welded a splint onto damaged steelwork.The first cars were allowed back onto the crossing at 05:20 after engineers welded a splint onto damaged steelwork.
Heavy goods vehicles will remain banned until further work is carried out, with this scheduled for completion by "mid-February".Heavy goods vehicles will remain banned until further work is carried out, with this scheduled for completion by "mid-February".
The bridge was closed to all traffic on 4 December after a crack was discovered in a truss under the carriageway.The bridge was closed to all traffic on 4 December after a crack was discovered in a truss under the carriageway.
In normal operation, the bridge handles 80,000 vehicles each day and closure has caused significant disruption.In normal operation, the bridge handles 80,000 vehicles each day and closure has caused significant disruption.
Bridge operator, Amey, said: "Traffic has been running very well all day since the bridge reopened. There have been no queues and no delays."Bridge operator, Amey, said: "Traffic has been running very well all day since the bridge reopened. There have been no queues and no delays."
The partial re-opening is ahead of schedule, with officials having previously estimated that the temporary repairs would not be completed until after the Christmas holidays.The partial re-opening is ahead of schedule, with officials having previously estimated that the temporary repairs would not be completed until after the Christmas holidays.
But the ban on HGVs is longer than expected. Road Haulage Association chief executive Richard Burnett said it would have a "massive impact".But the ban on HGVs is longer than expected. Road Haulage Association chief executive Richard Burnett said it would have a "massive impact".
"The major distribution centres on the northern, Fife-side of the river are totally reliant on an efficient, swift transport system and we have had many reports from members who are already struggling to keep to their pre-Christmas delivery schedules," he said."The major distribution centres on the northern, Fife-side of the river are totally reliant on an efficient, swift transport system and we have had many reports from members who are already struggling to keep to their pre-Christmas delivery schedules," he said.
"The news that they will continue to face delays and a massive increase in cost for another eight weeks will, for many, prove to be unsustainable.""The news that they will continue to face delays and a massive increase in cost for another eight weeks will, for many, prove to be unsustainable."
Chris MacRae from the Freight Transport Association said: "A lot of our members are going to be very upset to put it mildly, that they were planning for a fourth of January return and now it's an unspecified date in the middle of February.Chris MacRae from the Freight Transport Association said: "A lot of our members are going to be very upset to put it mildly, that they were planning for a fourth of January return and now it's an unspecified date in the middle of February.
"That cannot be allowed to slip again. It has to reopen to HGVs in the middle of February and we have to have a date for that as soon as possible.""That cannot be allowed to slip again. It has to reopen to HGVs in the middle of February and we have to have a date for that as soon as possible."
Police officers were stationed at both ends of the bridge on Wednesday to redirect any vehicle over 7.5 tonnes.Police officers were stationed at both ends of the bridge on Wednesday to redirect any vehicle over 7.5 tonnes.
A police spokesman said the continued ban on HGVs was being well adhered to. A police spokesman said the continued ban on HGVs was being well adhered to. By midday five lorries had been turned away.
HGVs account for 32% of the weight the bridge normally carries despite making up approx 9% of overall traffic.HGVs account for 32% of the weight the bridge normally carries despite making up approx 9% of overall traffic.
Scottish government transport minister Derek Mackay said the estimated reopening date for HGVs of mid-February "felt accurate" based on the work programme but it was weather dependent and assumed no further faults were found.Scottish government transport minister Derek Mackay said the estimated reopening date for HGVs of mid-February "felt accurate" based on the work programme but it was weather dependent and assumed no further faults were found.
He told the BBC's Good Morning Scotland programme: "I am very certain that we'll meet that date of mid-February for the bridge to be open to HGVs.He told the BBC's Good Morning Scotland programme: "I am very certain that we'll meet that date of mid-February for the bridge to be open to HGVs.
"Of course it's good news this morning that it's open to 90% of traffic and HGVs should follow early next year. Mid-February is as accurate a date I can give based on engineers' opinion at this time.""Of course it's good news this morning that it's open to 90% of traffic and HGVs should follow early next year. Mid-February is as accurate a date I can give based on engineers' opinion at this time."
Mr Mackay said the revised date for full reopening was based on data gathered from load testing.Mr Mackay said the revised date for full reopening was based on data gathered from load testing.
"We weren't satisfied with the results. That's why further strengthening works are required. It's partly a precautionary measure to give us absolute certainly that it's safe and effective to allow HGVs across from mid February.""We weren't satisfied with the results. That's why further strengthening works are required. It's partly a precautionary measure to give us absolute certainly that it's safe and effective to allow HGVs across from mid February."